How We (TerraForma Drilling) Solved a Tight-Access Site Investigation Without Compromising the Bore Plan
Geotechnical Drilling

How We (TerraForma Drilling) Solved a Tight-Access Site Investigation Without Compromising the Bore Plan

4 boreholes at a narrow Inner West Sydney site in 1 day. Ute-mounted SFA rig through a sub-3m driveway. Full bore plan completed without relocating a single borehole.

Inner West SydneyView Case Study
22 Boreholes Delivered in 4 Days: We Coordinated Geotechnical Drilling Across 5 Greater Sydney Sites
Geotechnical Drilling

22 Boreholes Delivered in 4 Days: We Coordinated Geotechnical Drilling Across 5 Greater Sydney Sites

22 boreholes across 5 Greater Sydney sites in 4 days. Progressive bore logs issued as each site completed. One drilling subcontractor, consistent field procedures throughout.

Greater SydneyView Case Study
12 Locations, 1 Field Day, No Shutdown: How We Completed a Pavement Subgrade Investigation Around Active Operations
Geotechnical Drilling

12 Locations, 1 Field Day, No Shutdown: How We Completed a Pavement Subgrade Investigation Around Active Operations

12 DCP test locations completed in a single field day around active operations at a Western Sydney logistics facility. Ute-mounted SFA rig. Zero shutdown required.

Western SydneyView Case Study
TerraForma Drilling Turned a Detailed Bore Specification Into Four Monitoring-Ready Installations
Groundwater Well Installation

TerraForma Drilling Turned a Detailed Bore Specification Into Four Monitoring-Ready Installations

4 monitoring bores installed to consultant specification in 2 days at a Northern Beaches Sydney property. PVC casing, screen intervals, filter pack, and bore construction records.

Northern Beaches, SydneyView Case Study
How TerraForma Drilling Completed a Phase 2 DSI Without Compromising Sample Integrity
Environmental Drilling

How TerraForma Drilling Completed a Phase 2 DSI Without Compromising Sample Integrity

8 boreholes completed across a former industrial site in South Western Sydney in 2 days. Strict decontamination between every borehole. Sample integrity maintained throughout.

South Western SydneyView Case Study
When a Drilling Subcontractor Pulled Out, TerraForma Drilling Mobilised Within 24 Hours
Geotechnical Drilling

When a Drilling Subcontractor Pulled Out, TerraForma Drilling Mobilised Within 24 Hours

Drilling subcontractor withdrew at short notice on a Western Sydney project. TerraForma quoted same day and mobilised within 24 hours. Investigation completed on programme.

Western SydneyView Case Study

Do You Have a Site with Unique Access or Investigation Needs?

TerraForma Drilling offers practical geotechnical and environmental field support throughout Sydney and regional New South Wales.